The 15-Minute Daily Meeting That Keeps Lean Improvements From Fading

A ready to run agenda, board layout and KPI set for team leaders, and how to escalate problems in hours rather than at month end.

It’s the second week of the month, and the operations pack has just landed in your inbox. Forty odd slides. Somewhere around slide twenty-three there’s a chart showing scrap on one of your lines. It’s been creeping up since the third of last month. Not a spike. Just a slow climb, from about 2% to nearly 6%, week after week.

So you ask the obvious question. When did we know?

And the honest answer, if you dig for it, is that the operators knew on the third. The team leader knew by the end of that week. The quality engineer had a hunch it was a material batch issue by the following Tuesday. The information was in the building the whole time. It just took five weeks to travel about two hundred metres, from the line to the people who could make a decision about it.

That’s the thing I’d want you to sit with for a second. Nobody hid it. It simply had no route to travel quickly, so it waited for the one meeting that was guaranteed to happen. Month end.

Now think about how a good automotive line handles a problem. An operator pulls the Andon cord, and the team leader is there within seconds. If they can’t sort it inside the cycle, it goes up again, to a group leader inside about a minute, and to an engineer or manager within a few minutes more. Toyota’s plant in Georgetown, Kentucky has reported thousands of Andon pulls in a typical day. Escalation measured in seconds.

Most mid to large UK manufacturers sit somewhere between those two worlds. You’ve probably got a morning meeting of some kind. But if I’m honest, in a lot of the factories I walk into, it’s a seated meeting in an office, it runs well past half an hour, and the problems it discusses are already a day or a week old.

We wrote about this years ago on our old Managing Business Performance page, back when we called them operations rooms. A lot of what we said then still holds. Red and green only. A handful of measures, not dozens. Problems get a countermeasure, not a deferral. But I’d change two things now. Thirty minutes is too long for the meeting at the team board. And one meeting isn’t enough. You need a short chain of them, linked, so a problem raised at half six can reach someone with authority before nine.

I first learned to run a meeting standing at a board as a young engineer in the early nineties, and I’ve been on both sides of it since: running the board, and being the manager the problems got escalated to. So this post is the practical version. Why improvements fade. How three short tiers move a problem up in hours. What the board should look like. The KPI set your team leaders can use from Monday. And how to stop the meeting itself from fading, which, to be fair, it will try to do.

Why your improvements fade

You’ve probably seen this happen. A kaizen week goes brilliantly. The team’s buzzing, the numbers look great at the report out, and somebody takes a photo of the new cell layout for the newsletter. Six months later, you walk past and it’s quietly drifted back towards how it used to be.

It isn’t just you. In 2018, Matthias Holweg, Bradley Staats and David Upton published research in Harvard Business Review that followed 204 lean improvement projects at a large bank across 14 countries over four years. Around one in five projects delivered nothing at all. Of the ones that did, a big share slid back within a year, and by the two-year mark fewer than half were still holding their gains.

The more interesting finding, I think, was about leadership. Projects with strong support from head office were far less likely to backslide: 79% were still above their starting point after a year, against 61% of those without that support. The researchers were pretty blunt about the reason. A continuous improvement culture doesn’t just emerge from the workforce on its own. Leaders have to keep engaging with it, as a habit, long after the launch.

They also named four ways it goes wrong, and you’ll probably recognise at least two. Initiative fatigue, where leaders move on to the next thing. Tool overzeal, where a stalled effort gets “relaunched” with a new methodology. Chasing short term metrics that don’t really match what the business is trying to do. And dogmatic rollouts that leave the people doing the work with nothing meaningful to contribute.

Michael Ballé at the Lean Enterprise Institute makes a point I’ve always liked. Starting 5S isn’t hard. Keeping it is, because keeping it means changing the way people work every single day. That’s a different job entirely.

I saw this play out with an aerospace composites business in Lancashire, around 450 people. They ran a really good changeover week on a press that fed their main curing line, and got a 90-minute changeover down to 35. Proper work, properly done. Four months later it was averaging about 70 again. Nobody had decided to go back. The changeover cart got borrowed. A new setter started who hadn’t been on the event. One busy week, the prestaging didn’t happen, and the next week nobody noticed.

What fixed it wasn’t another event. It was putting changeover time on the team’s daily board, with a red line at 40 minutes, and making it the first thing the team leader looked at every morning. Within about six weeks it was back under 40, and it stayed there.

So here’s how I’d put it. The improvement event wins the gain. The daily meeting is what keeps it.

Three tiers, one morning

The idea behind tiered daily management is simple. Instead of one big meeting, you run a short chain of them, each one standing at its own board, each feeding the next, all inside the first couple of hours of the shift.

Here’s a version that works for a lot of mid to large sites on a 06:00 day shift. Shift the times to suit yours, but keep the gaps.

Tier 1, the team, 06:30, 15 minutes. The team leader and their crew, five to fifteen people, standing at the team board in the work area. Yesterday’s performance, today’s risks, and actions the team owns.

Tier 2, the area or value stream, 07:15, 15 minutes. The area manager, the tier 1 team leaders, and someone each from maintenance, quality, planning and materials. Only reds and escalations. A green team gets a nod, not a recap.

Tier 3, the site, 08:15, 15 to 20 minutes. The operations director or site manager and the heads of function. Site trends, resource clashes, and the decisions that need authority or money.

The gaps matter. Twenty to thirty minutes between tiers gives leaders time to walk from board to board and means escalations arrive fresh rather than as second hand summaries. If your site’s smaller, two tiers is fine: team and site. The mechanics are the same.

What makes it a system rather than three separate meetings is the escalation. So write the rules down and pin them next to every board. Something like this:

  1. The team fixes it. If the team can sort it with its own people and tools, it goes on the board as an action with an owner and a date, and it’s closed within 24 hours.
  2. It goes up the same morning. If the fix needs another function, affects safety, has happened three times in a fortnight, or has kept a measure red for two days running, it goes on the escalation lane at tier 1 and gets raised at tier 2 that morning. Safety concerns don’t wait for any meeting at all.
  3. An answer comes back the same shift. Every escalation that’s accepted gets a named owner and a response time. The team gets at least an interim answer before the shift ends: a fix, a dated plan, or an honest reason why not.
  4. Nothing ages quietly. No escalation lives longer than 48 hours without an owner and a date. If it does, it goes straight to the next tier up.

Think of the whole thing as a clock. A month end review moves problems in weeks. A weekly meeting moves them in days. A working tier system moves them in hours. Andon moves them in seconds. You don’t need to be Toyota tomorrow. Moving from weeks to hours is a huge step on its own.

The physical detail that holds all this together is what I’d call the escalation lane. A strip on every board with four columns: what the problem is, when it was raised, who owns it, and when it was answered. If an escalation only exists in somebody’s notebook, it’s already in trouble, because nobody can see it getting older.

I remember a team leader at a chilled food plant in Lincolnshire, a site of about 600 people. When we went back through her shift log, she’d written up the same sticking conveyor guard eleven times in three months. Eleven. Every entry was polite and accurate. None of them had an owner. The first week it went on an escalation lane with a date next to it, maintenance had it fixed in two days. She wasn’t cross about it, which honestly surprised me. She just said, “I thought somebody was reading those.”

The board: what goes where

The board is the meeting. If it isn’t on the board, it isn’t in the meeting. That sounds strict, but it’s the single rule that stops a 15-minute stand up turning into a 45-minute chat about whatever’s on people’s minds.

Here’s a layout that works for most team boards, reading left to right.

Header strip. Team name, date and shift. Who’s in, who’s off, and how the gaps are covered. A simple skills cover grid, showing who’s trained on which station, earns its place here more often than you’d think.

SQCDP letters. One panel each for safety, quality, cost, delivery and people. Each has a letter tracker, which is the big letter divided into one box per day of the month, coloured red or green. Under each letter, a small trend chart with the target drawn on it, so you can see whether today’s red is a blip or the third in a week.

Problems and countermeasures. Every red gets a line: what happened, the containment for today, one action, an owner and a due date. Old fashioned, I know. It works.

The escalation lane. As above. What, raised when, owner, answered when.

Standards we’re protecting. This is the strip most boards are missing, and it’s the one that ties the meeting to your lean work. List the two or three improvements this team has made recently, with the measure that proves each one is holding. Changeover time on the press. 5S audit score in the cell. First off approval time. If one slips, it goes red like everything else.

Today. The plan, the biggest risk, and the standard agenda printed at the bottom so anybody can run the meeting.

A few rules from our old operations room days still stand up. Use red and green only. Amber is where problems go to hide. Keep to between three and six measures the team can actually influence. And get yesterday’s numbers on the board before the meeting starts, not during it. If the data turns up at lunchtime, your 06:30 meeting is really a meeting about the day before yesterday.

What about digital boards? If you’ve got machine monitoring feeding live OEE and downtime to a screen, brilliant. It saves somebody a 05:45 spreadsheet ritual. But I’d still start with a whiteboard and marker pens, and I’d keep the conversation standing at the board either way. The screen is the data. The meeting is people deciding what to do about it.

The KPI set and the 15-minute agenda

People often ask me for “the” KPI list. There isn’t one, to be honest. But here’s a starting set for a team leader that I’ve seen work in machining, assembly, food and process plants, with one main measure per letter and a supporting one where it helps.

Safety. Accidents and near misses reported yesterday. Yes, reported. A team that reports near misses is healthier than one that never seems to have any. Supporting: open safety actions.

Quality. Right first-time percentage, or scrap and rework count. Supporting: internal and customer complaints traced back to this team.

Cost. Scrap value or labour hours against standard. Supporting: overtime hours.

Delivery. Plan attainment, meaning what we said we’d make yesterday against what we made. Supporting: OEE or the biggest downtime cause on the constraint machine.

People. Attendance and skills cover. Supporting: improvement ideas raised and implemented this month.

Then, for tier 2, the area manager sees the same letters rolled up by team, plus the escalation lane for the whole area. At tier 3, the site leadership sees safety, on time in full to customers, cost of poor quality, output against plan at the constraint, and one more number that I’d argue matters as much as any of them: how many escalations are open, and how old the oldest one is.

Now the agenda. Same order every day, so it runs on rhythm rather than on whoever’s facilitating.

Minutes 0 to 2: safety and people. Anything that happened, any near misses, who’s missing and how we’re covering.

Minutes 2 to 6: yesterday against target. Walk the letters. The team calls each one red or green, not the team leader. That small shift matters more than it looks.

Minutes 6 to 10: the reds. For each one: what happened, how we’re containing it today, one action, one owner, one date. No root cause hunting here. That happens after the meeting with the people who are needed.

Minutes 10 to 12: yesterday’s actions and our standards. Did what we said we’d do actually get done? Are the improvements on our “protecting” strip holding?

Minutes 12 to 14: escalate. What can’t we fix ourselves? One sentence each on the lane, with the impact in units, minutes or pounds.

Minutes 14 to 15: today. The plan and the one thing most likely to go wrong.

Standing up isn’t just a lean habit, by the way. Back in 1999, Allen Bluedorn and colleagues at the University of Missouri compared more than a hundred five person groups and found sit down meetings ran 34% longer than stand up ones, with no better decisions to show for it. Standing keeps you honest about the clock.

A handful of ground rules stop the meeting going soft. Start on time, even if the boss is late. Especially if the boss is late. No chairs and no laptops. Challenge with respect, which was on our old page, and I’d keep word for word. And anything that needs more than a couple of minutes leaves the meeting with a name and a time attached.

Keeping the meeting from fading too

Here’s the slightly awkward truth. The daily meeting is the thing that stops your improvements fading, and the daily meeting will try to fade as well. It rarely dies loudly. It just gets a bit longer, then moves into the office “because it’s cold out there”, then somebody brings a laptop, then the area manager starts sending apologies. Three months later it’s a status update with chairs.

David Mann, in Creating a Lean Culture, describes a lean management system as four things working together: leader standard work, visual controls, a daily accountability process and leadership discipline. The meeting and the board are only two of them. The other two are about what leaders do, every day, to keep them honest.

So build that into the routine of every manager above tier 1.

Attend one tier 1 a day as a coach, not the chair. The area manager stands at the back, says almost nothing, and gives the team leader two minutes of feedback afterwards. Rotate round the teams.

Audit the meeting monthly. A manager from a different area watches one meeting and asks five questions. Did it start on time, standing, at the board? Did it finish inside 15 minutes? Was yesterday’s data up before it started? Does every red have an owner and a date? Did every open escalation get a status?

Rotate who facilitates. Every week or two, someone else in the team runs it. The meeting then survives holidays, sickness and promotions.

Measure the system itself. Track two numbers at tier 3: the average age of open actions, and how long escalations take to get answered. If either starts creeping up, the system’s fading, whatever the SQCDP letters say.

And please, invest in the people running the board. Research from the Chartered Management Institute found that 82% of people stepping into management roles in the UK have had no formal management or leadership training. On a factory floor, the person running your tier 1 was quite possibly your best operator eighteen months ago. Running a sharp, fair, 15-minute meeting in front of their old mates is a genuine leadership skill. It needs teaching and coaching, not just a laminated agenda.

One last thing, and it’s maybe the most important. In my experience, tier meetings almost never die because people get bored of them. They die because escalations stop coming back answered. A team leader raises something, it disappears upstairs, nothing happens, and after the third time they stop raising things. Why wouldn’t they? So if you only check one thing as a senior leader, check that. Every escalation, answered, visibly, on the board that raised it.

Hours, not weeks

So, back to that month end pack, and the scrap that climbed for five weeks before anyone with authority saw it.

With a working tier system, that story looks different. The operators flag rising scrap at tier 1 on day one. By day two it’s red for the second time, so it goes on the escalation lane. Quality picks it up at tier 2 that morning, with a response time. By the end of the shift there’s a containment in place and a suspect material batch quarantined. The month end pack still shows it, but as a small blip with a note next to it. Not five weeks of cost.

That’s really the whole case. Improvements fade because nobody checks the new standard every day. A 15-minute meeting at a board, linked to two more short meetings above it, checks it every day and moves problems up in hours. Keep the board simple, with red and green, three to six measures, a problems log, an escalation lane and a strip for the standards you’re protecting. Use a fixed agenda. Write down your escalation rules. Then make sure your managers coach the meeting, audit it, and above all answer what comes up to them.

If you’d like a hand setting this up, it’s exactly the kind of thing we do at TCMUK. Our Lean Coaching and Mentoring Programme trains your teams on site and then coaches your own people through live projects, with check ins at days 10, 30, 60, 90 and 120, so the daily management system is built by your team rather than handed to them. And if your team leaders are new to leading people, our Helping Managers to Succeed and Lead Programme gives them a mentor and practical tools for running teams day to day. Or, if you’d just like to talk through how your morning meetings work now, book a 15-minute call with Adam. No pitch. Just a conversation.

Your factory probably already knows about most of its problems. The question is how long it takes that knowledge to reach someone who can act on it.

Get your Changeovers out of the Slow Lane

Why long set ups quietly cap your capacity, and how SMED gets the time back without buying another machine.

There’s a conversation I’ve heard in more factories than I can remember. A key machine is “at capacity.” A customer’s getting nervous. Somebody puts a quote for a second machine on the MD’s desk, and the talk turns to finance, floor space and who on earth is going to run it.

And nobody, at any point, asks how much of the week that first machine actually spends making parts.

Whether you run a high-volume business or a low volume one, changeovers are one of those things that can quietly drain the life out of your manufacturing process. Left alone, an unstructured approach to set ups has a habit of growing arms and legs. Then the arms and legs grow arms and legs. Nobody plans it. It just creeps.

I first saw this properly in the early nineties. I was a Kaizen engineer at a business making aerospace fasteners, and we were being trained in lean manufacturing by a Japanese sensei. He split us into three teams for a week of improvement events on three different machines: a centreless grinder, a thread roller and a header machine. My team got the header.

The first thing we did was film a real changeover, start to finish. Not a demonstration. The real thing, done the way it had always been done.

When we added it up, there were eight hours of it. A whole shift. For a production run that would last thirty minutes to an hour, depending on batch size, and we were talking batches in the thousands. The machine ran three shifts, so a big slice of its working life was spent getting ready to work.

And here’s the bit that still makes me smile. A major customer had flagged that machine as a high risk to their supply because of capacity. They were actively pushing us towards buying another one.

At the start of the week, we’d have been delighted with a 50% reduction. Honestly, that felt ambitious. Never in a million years did we think we’d get it under thirty minutes. But we did.

That week changed how I look at every factory I walk into. So this post is the longer version of what I learned, brought up to date for UK manufacturing in 2026. What long changeovers really cost you, why you should film one before you touch anything, how to split internal work from external work, and the three words that have stuck with me for over thirty years: eliminate, combine, simplify.

What a long changeover is really costing you

Most people think of a changeover as lost machine time. It is. But I think that’s the smallest part of the bill.

The bigger cost is what long changeovers force you to do to cope with them. If a set up takes half a shift, nobody wants to do it often. So you run bigger batches. Bigger batches mean more work in progress on the floor, more finished goods in the stores, more cash tied up in stock and more floor space lost to racking. You make things before anybody’s ordered them, which is overproduction, the waste that tends to feed all the others. Jobs wait in a queue behind the big run. Material gets moved, stacked, then moved again. Lead times stretch, so you quote longer, so customers order earlier and in bigger lumps, and round it goes.

In other words, a long changeover doesn’t just waste an hour. It sets your batch size. And your batch size quietly sets your stock, your lead times and a fair bit of your cash flow.

There’s a nice bit of history here. For most of the twentieth century, factories worked out batch sizes using the economic order quantity, a formula that treats set up time as a fixed cost you simply have to live with. Toyota’s big insight was to question the “fixed” part. If changeovers get short enough, the economic batch gets small, and suddenly you can make what customers actually want, when they want it.

That matters more for UK manufacturers now than it did when I was stood next to that header machine. A lot of your customers want smaller quantities, more variants and shorter lead times, and they don’t want to pay for you holding their stock. For plenty of UK firms, high mix, low volume isn’t a niche anymore. It’s just the work.

Then there’s capacity. Make UK’s Q3 2026 Manufacturing Outlook showed the UK orders balance rising from +12% to +17%, but manufacturers holding back on hiring because employment, energy and input costs are still biting. More orders. Same people. Same machines. So where’s the extra output meant to come from?

Before you sign off a second machine, or another shift you can’t staff, it’s worth asking a slightly awkward question. How much capacity is already sitting inside your changeovers, waiting to be found?

In my experience, it’s usually more than anyone guesses. Quite a lot more.

Film it before you fix it

If you take one thing from this post, make it this. Before anyone suggests a single improvement, film a real changeover.

Not a rehearsed one. Not the one your best setter does when he knows the MD’s watching. The normal one, on a normal day, from the last good part of the old job to the first good part of the new one. That’s the bit that counts, by the way. The changeover isn’t finished when the new tool’s in. It’s finished when you’re making good parts at the right rate.

Why video? Because memory is hopeless at this. Ask a setter how long a changeover takes and you’ll get an honest answer that’s often wildly out, because nobody notices the walking, the waiting and the searching. They just feel like part of the job.

When you play the footage back with the team, a few things almost always jump out.

Walking. One practitioner wrote about watching an operator go to the tool store fourteen times in forty-five minutes, collecting one tool at a time. I’ve seen versions of that more often than I’d like to admit.

Searching. For the right spanner, the right insert, the drawing, the program, the forklift, the person with the key to the cabinet.

Waiting. For the crane, for quality to sign off a first off, for material nobody brought up because nobody knew the job was next.

Adjusting. Run a part, measure it, tweak, run another, measure again.

That last one is the big one, and it surprises people. Shigeo Shingo, the Japanese engineer most closely associated with quick changeover, broke a typical set up into four chunks. Preparing and checking tools and materials took about 30% of the time. Centring, dimensioning and setting conditions took about 15%. Trial runs and adjustments took about 50%. And actually mounting and removing the tool? Around 5%.

Five percent. The bit everyone pictures when they think “changeover” is barely a rounding error. The rest is preparation and guesswork.

A quick word on how you film it, because it matters. Tell people why you’re doing it. Make it clear you’re studying the process, not the person. The setter on that footage is usually the one who knows exactly where the time goes and has been quietly frustrated by it for years. Put them in the room when you watch it back, and let them talk first. You’ll learn more in an hour than in a month of stopwatch studies.

Then map it. List every step, how long it took and who did it. A simple spaghetti diagram, which is just a sketch of the machine with a line drawn wherever the operator walked, is brilliant for this. If it looks like someone’s dropped a plate of spaghetti on the drawing, well, you’ve found some easy wins.

Internal and external: the split that changes everything

Once you’ve got the list of steps, there’s one question to ask of every single one.

Does the machine have to be stopped to do this?

If it does, it’s internal set up. Taking the old tool out. Fitting the new one. A few genuine settings. That work can only happen when the process is stood.

If it doesn’t, it’s external set up. Fetching the tools. Finding the drawing. Bringing the material to the machine. Preheating a mould or die. Presetting tools off the machine. Checking you’ve got the right fixings. All of that can happen while the last job is still running.

The principle is simple, and it was the backbone of everything we did on the header machine. Do as much of the work as you can while the machine’s still running. Keep internal work to the absolute minimum, ideally just fitting and removing the tool, die or material, and nothing else.

I’d almost guarantee you’ll find that a lot of what’s being done with the machine stopped didn’t need the machine stopped at all. It’s just always been done that way. The setter stops the machine, then goes to look for the tooling. Nobody ever decided that was the right order. It just became the order.

Shingo described the journey in roughly four stages. First, make sure anything external really is done while the machine runs. Second, separate internal from external properly, so everyone can see which is which. Third, convert as much internal work as you can into external work. Fourth, improve everything that’s left.

Toyota’s big press changeovers are the classic example, and I think they’re worth knowing because they show how much of this is about preparation rather than clever engineering. Their huge stamping dies were being positioned by eye and nudged with crowbars, with test pressings in between, and a change could take anywhere from twelve hours to nearly three days. The first improvement was simply to record the right measurements for each die and set to those rather than by eye. That alone took it down to about an hour and a half. Then came staging the next die and the crane before the old one came out, and keeping the right tools at the press. Eventually it got to under ten minutes per die.

That’s where the name comes from. SMED stands for single minute exchange of die, but “single minute” means a single digit, so under ten minutes, not literally sixty seconds. Shingo usually gets the credit, though to be fair the history’s a bit more tangled than that, and Toyota’s engineers had been chipping away at changeover times since the forties. Shingo also claimed his own data showed set up times falling, on average, to around 2.5% of where they started. Maybe take that with a pinch of salt. But even a fraction of it would change most factories I know.

You can start moving work external without spending much at all:

Changeover kits or carts. Everything the job needs, tools, fixings, gauges and paperwork, staged at the machine before it stops.

A visible schedule. If the setter doesn’t know what’s next, they can’t prepare for it. A simple board showing the next two jobs fixes more than you’d think.

Preheating and presetting. Warm the mould, preset the tools, load the program, all while the current job finishes.

First off checks planned in. Agree with quality in advance when they’ll be needed, rather than waiting for someone to wander over.

Eliminate, combine, simplify

The phrase that’s stuck in my head since those early events is three words. Eliminate, combine, simplify.

It comes from a framework Toyota borrowed from the American Training Within Industry programme of the Second World War, usually written as eliminate, combine, rearrange and simplify. I’ve always remembered it as three, and to be honest three’s easier to keep on a whiteboard anyway.

Take whatever internal work is left and run each step through those words, in order.

Eliminate first. Can you stop doing this step altogether? Shingo had a lovely observation about bolts: it’s only the last turn that actually tightens it. Everything before that is just movement. So if a clamp needs twelve turns of a bolt, that’s eleven turns of waste on every changeover. Quarter turn fasteners, cam clamps, keyhole slots and quick release fittings all attack that. And do you really need eight bolts holding something that four would hold safely?

Adjustments are the other big target. Every adjustment is a sign that something isn’t located in the right place. Locating pins, fixed stops, spacers cut to height and marked datum lines can turn “fiddle until it’s right” into “fit it and it’s right.”

Then combine. Can two steps happen at once? Two people working in parallel, one each side of the machine, can sometimes halve what’s left of the internal time. It needs a bit of choreography, and you’ve got to think hard about safety, but it’s often worth it on a bottleneck machine.

Then simplify. Make whatever’s left easy and hard to get wrong. Standardise tool heights so everything sits at the same shut height. Use the same size fixing everywhere so one spanner does the lot. Colour code. Put a photo of the finished set up on the machine. Shingo called this standardising function rather than shape. Your tools don’t all need to be identical. They just need to fit and locate the same way.

A word of warning, from experience. Don’t start with the engineering. Teams love designing a clever quick release fixture, and fair enough, it’s the fun bit. But the cheap stuff, the cart, the schedule, the staging and the checklist, usually gets you a big chunk of the gain for very little money. Get that in first. Then spend engineering time on what’s left, once you can see what really matters.

On the header machine, if I remember rightly, a lot of our first day’s gains came from nothing more sophisticated than a trolley, a marker pen and a bit of agreement about who fetched what. The clever bits came later in the week.

Making it stick, and spending the time wisely

Here’s the frustrating part. A great SMED week can quietly unravel within a couple of months if nothing holds it in place. New setter, mad week, the cart gets borrowed for something else, and before you know it the machine’s stood while someone goes looking for an insert again.

A few things help.

Write the new standard down. A one-page changeover standard, ideally with photos, kept at the machine. Who does what, in what order, and what “ready” looks like before the machine stops.

Put changeover time on the board. If you’ve got a daily production board, add changeover time to it. What gets looked at every morning gets talked about. What gets talked about tends to hold.

Check the kit, not just the clock. A quick audit of the changeover cart once a week catches the slow drift before it costs you.

Go round again. A common rule of thumb is that each serious pass through the process takes out somewhere around 45% of what’s left. So a two-hour changeover might need a few rounds before it gets anywhere near ten minutes. That’s normal. It’s a loop, not a project.

Then there’s a question most teams forget to ask until it’s too late. What are you going to do with the time you’ve saved?

It’s tempting to keep running the same big batches and pocket the extra hours as output. Sometimes that’s the right call, especially if the machine’s a genuine bottleneck and the order books full. But often the bigger prize is changing over more often, running smaller batches, and taking stock and lead time out of the whole business. The hours you win back on the machine can come back to you as cash in the bank, space on the floor and shorter quotes for your customers.

I’d decide that on purpose, as a leadership team, rather than letting it happen by default. Otherwise, you tend to end up with neither.

Bringing it back to the header machine

Let’s pull it together.

Long changeovers do more damage than the minutes on the clock suggest. They push you into big batches, and big batches drive work in progress, finished stock, overproduction, waiting and endless moving of material. And with orders improving across UK manufacturing while hiring stays cautious, the capacity hiding inside your changeovers might be the cheapest capacity you’ll ever find.

The method isn’t complicated. Film a real changeover and watch it with the people who do it. Split internal from external, and move everything you can to while the machine’s still running. Then take what’s left and eliminate, combine and simplify. Standardise it, measure it daily and go round again.

Think back to that customer pushing us to buy another header machine. We never needed it. The capacity was there all along. It was just spending a whole shift at a time getting ready to work.

So before you sign off on new kit, film your worst changeover. You might be surprised. I usually am, even now.

If you’d like a hand, this is exactly the kind of thing we do at TCMUK. Our Lean Coaching and Mentoring Programme trains your own people in tools like SMED and then coaches them through live projects on your shop floor, so the gains belong to your team and keep coming long after we’ve gone. You can read more about the Lean Coaching and Mentoring Programme, or book a 15 minute call with Adam to talk through the changeover that’s causing you the most grief. No pitch. Just a conversation about whether we can help. Your machines are probably far more capable than your changeovers are letting them be.